Dominique O’Rourke
When the transit expansion plan came to council, in 2021, these were the financial assumptions presented to Council and the funding approved by Council (below). Are the funding implications still the same or higher? If they are higher, by how much? If they are higher, what would it mean to hold them in line with the originally anticipated increases?
 
The document also says "converting all buses to electric over the next 15+ years" are we working at this pace? Faster?
 
From the Future Ready Action Plan
 
Financial summary
The Future Ready Action Plan has estimated operating expenses at implementation
of $17.21 million and projected revenues of $4.12 million, which has a net cost of
$13.08 million. The estimated annual net operating cost for 2022 and 2023 of the
Future Ready Action Plan is $1.77 million and $1.26 million, respectively, which
represents a 0.67 percent property tax levy increase for 2022 and 0.45 percent for
2023.
In addition, tax funding is required to support the goal of 100RE by converting all
buses to electric over the next 15+ years and the portions of the plan which are
considered City Building. This funding was approved by Council as part of the
Strategic Investment that was presented at the 2022 City Budget Council meeting.
$850,000 is required to fund 100RE annually, which represents 0.32 percent
property tax levy increase, and $716,100 is required annually for 10 years to fund
City Building, which represents a 0.27 percent property tax levy increase for 2022.
The total property tax levy impact needed to fund the Future Ready Action Plan as
well as fund the capital requirements of the total 10-year capital investment is a
1.26 percent increase for 2022 and 0.45 percent for 2023.
 
[234312%2F8462104%2Fmceclip0]
 
The total capital investment required over the next 10 years is $253.9 million; however, the direct
capital investment of the Future Ready Action Plan is only 15 per cent of this
amount, or $37.63 million, for the purchase of 26 buses. The 26 buses are funded
through development charges (40%), ICIP subsidies (44%), and the renewal
energy fund (16%) in the 10-year capital plan.
There are five full-time positions and one part-time position that council approved
for 2022, with a budget impact of $547,000, which represents 0.21 percent
property tax levy increase. In 2023, four full-time positions are required, with a
budget impact of $397,000, which represents 0.14 percent property tax levy
increase; three full-time positions in 2024, with a budget impact of $286,000,
which represents 0.09 percent increase to property tax levy; and one position in
2025 with a budget impact of $134,000, which represents 0.04 percent increase to
property tax.
Reply
sdevost

Yes, Transit Fleet electrification plan is on track and is expected to be completed in 15 years. Although there have been delays with electric bus deliveries, for example the first group of 4 electric buses ordered in 2021 were delivered and placed into service in late 2023. It is believed electric bus delivery timeline will improve over the years as electric buses become the standard.   

There were assumptions built into Future Ready Action Plan when presented in 2021. Since the plan was proposed there have been changes that impact the current proposed budget. This includes the deferral of inter-regional transit, deferral of Conestoga u-pass revenue, deferral of routes due to construction, and pulling forward service enhancements that exceeded council approved service standards. The original plan had $10.41 million in operating expenses from 2024-2028 and the current revised proposed plan has $10.38 million in operating expenses. Further the capital budget for this plan was submitted at $37.26 million and the current budget reflects this to now be $37.06 million.

In addition to the Future Ready Action Plan, this report included project information on the broader transit infrastructure required for bus fleet electrification  including the new transit facility as well as other transit-related improvement projects that were submitted in Phase 1 for Guelph’s portion of the Investing in Canada Infrastructure Program. Since that time, the City has also submitted applications for Phase 2 of funding as well but has not heard back on whether all projects have been approved. The project assumptions and costing for these transit-related infrastructure projects have changed significantly from the initial report in 2021, most notably being the cost of the transit facility, associated charging infrastructure and Guelph Central Station.  As indicated in the budget companion report to Council, on page 6 of 8, “In total for these projects, there is $331.5 million budgeted in the 2024 to 2033 forecast, in addition to the $40.1 million budgeted in 2023 and prior. Staff are working to assess how to reduce the tax-funded cost of this program overall while continuing to leverage the grant funding. Staff will be reporting back to Council on the outcome of this work in 2024 either before or as part of the budget confirmation.