Dominique O’Rourke
TC0072 Digital signs has been an identified project for the last two budgets and I believe still not implemented.
Capital costs are $6.8million from 2024-2033, $1.8M of which are planned for 2024-2027.
Operational impact associated with the Digital for the next 3 years total $626,600 with an additional $300K in 2029.
 
I understand there is ICIP funding here but 
1. Can the digital sign project be cancelled?
2. If it cannot be cancelled, can it be rescoped significantly?
 
Further, why have the costs escalated significantly from the 2022-23 budget estimate for the same code?
Capital
[234312%2F8443372%2Fmceclip0]
 
Operating
[234312%2F8443376%2Fmceclip0]
Reply
Dominique O’Rourke
Further to my initial question. If there is zero capital for this project in 2024, why is there a 257,600 operational cost in 2024? 
 
[234312%2F8457772%2Fmceclip0]
 
longer time horizon
[234312%2F8457792%2Fmceclip0]
 
Operating impact from capital starting in 2024.
[234312%2F8457793%2Fmceclip0]
Reply
wmcquade
Reply to Can the digital sign project be cancelled?
 

The digital sign RFP is planned to be issued in January of 2024. While not recommended due to improved customer satisfaction and operating efficiencies, should Council direct staff to modify or cancel the project, it could be changed.

 

Reply to If it cannot be cancelled, can it be rescoped significantly?

 

The digital sign project is designed to be phased in over several years. There is the ability rescope and or spread out the project over several years.  Digital signs provide customers with real time information to customers along with service alerts. This allows customers to track the location of their bus and be notified of service alerts. This technology is especially helpful to customers without access to internet/data. We can re-prioritize, rescope and spread the project out over several years if directed.

 

Reply to Further, why have the costs escalated significantly from the 2022-23 budget estimate for the same code?

 

The costs have gone up as we are expanding the project to replace all static information posts throughout the city. There are approximately 600 bus stops with approximately 915 information posts spread across these bus stops. We can prioritize the list of locations, rescope and spread the project over several years if directed.

Currently Transit has paper information posts which requires a significant amount of staffing and or external resources to print, remove and install. The current manual process results in the delay of updated bus arrival information at bus stops which at times are significant service changes. Digitization of the static information posts provides customers with up to date real bus information which is especially important to customers without access to internet/data.

 

Other considerations:

The phase 2 of this digital signs project is currently funded in part by ICIP grant revenues along with bus shelters as a combined project under the ICIP grant. Based on the application/agreement the combined total project cost which includes bus shelters and digital signs was reported as $5.1M with a total recipient contribution of $1.4M (26.67% of total project costs). If digital signs are deprioritized, there may be an opportunity to shift this portion of the grant funding to the Transit Operations Facility to further help with the overall tax pressures on this program however approval would be under ICIP authority.   

 

 

Reply
wmcquade
Reply to 

If there is zero capital for this project in 2024, why is there a 257,600 operational cost in 2024? 

 

The $257,600 in 2024 is the operating impact of the 2023 capital budget of digital signs.

 

Reply
Dominique O’Rourke
I don't believe there is a need to have these signs at all bus stops. People come out of their homes or workplaces where they can get their bus information. What is the cost - and corresponding reduction - to have the signage at main hubs rather than at every stop? 
Reply
wmcquade

The greatest impact will be to customers who do not have access to data on a mobile device at the bus stops as they will not have real time information or service alerts. Digital signs should be at the top 100 stops.

 

Transit would require approximately $1.8 million in capital along with the operating costs of $269,000 in 2025 and $100,000 in 2026 to implement the signs at the top 100 stops. Currently the $1.8 million in capital is spread across 3 years (2025-2027); this could be spread over a longer time period if directed, with the operating impacts also correspondingly adjusted. In this case, Transit would continue with the very manual process of updating information posts at the remaining stops. The remaining capital of $5 million that is spread across from 2028-2031 could be removed should council only want to have digital signs at the top 100 stops. The associated $300,000 in operating impacts in 2029 would then be removed also. In addition, Transit can defer the previously approved 2024 operating impacts of $257,600 to 2025. There is minimal impact to delaying these operating impacts as the 2023 digital sign project is not likely to begin until Q4 2024.  The delay in digital sign project is due to rescoping of the RFP.

Reply
Dominique O’Rourke
What are the impacts if you do the top 50? 
Reply
wmcquade

To install 50 digital signs the capital cost would be $900,000 and the operating cost would be $184,000 spread across 2025 – 2028.

Reply
Reply