Rodrigo Goller
The draft budget states that “Asphalt and sidewalk renewal programs (i.e. annual paving, annual sidewalk, crack sealing, etc.) and new sidewalk gap infill continue but at a slower pace with some deferrals in terms of the overall budget requested through this time period.”
 
As I understand it, crack sealing is a cost-saving measure as it prolongs the lifespan of roads and sidewalks. It prevents more expensive road and sidewalk maintenance that is required when water and de-icing chemicals penetrate the road’s base layers, leading to potholes, extensive structural damage, accelerated deterioration, and significantly higher repair costs. Given Ontario's harsh freeze-thaw cycles, if we wanted to increase cost-savings, should we increase crack-filling rather than reducing our budget for this important maintenance work?
 
Please help me understand – by reducing the rate of crack filling, are we exposing ourselves to significantly higher maintenance and replacement costs in future years?
Reply
Daisy Zhang DaisyZhang
The Operations department will continue its crack sealing program without any reductions. This work is done through capital project RD0389 with just over $100 thousand budgeted annually through the 2026-2028 period. Some work was not completed in 2025 as the contractor was unavailable leaving a carry forward of $100 thousand for work in 2026.
 
However, the budget includes adjustments that slow or defer some road restoration, resurfacing, and new sidewalk construction.
  • RD0479 Road Restoration and Resurfacing Program was reduced by $1 million in 2026 leaving a budget of $3.5 million. In addition, RD0475 2025 Road Restoration and Resurfacing Program is projected to have a year-end carry forward of $900 thousand for work in 2026.
  • RD0480 and RD0481 Road Restoration and Resurfacing Program $500 thousand reduction in 2027 and 2028 respectively leaving a budget of $4.0 million in 2027 and $4.5 million in 2028.
  • RD0404 New Sidewalk Construction the 2026 budget has been removed but work will continue with the projected year-end carry forward in this account of just over $450 thousand.
Slowing these projects means:
- Delaying lifecycle maintenance: Restoring and resurfacing roads is a key part keeping them in good condition. Without this work, roads deteriorate more quickly, which increases risk of disrupting service levels for the community and may impact future maintenance activities.
- Increases to long-term costs: Deferred maintenance leads to more extensive and expensive repairs in the future.
- Achieving asset management program goals will take longer: Progress toward service level and infrastructure optimization will continue, but at a slower pace.
 
Reply