Can the South End Rec Centre or the Library be re-scoped to remove net-zero infrastructure? And if so, is there a cost savings and how much? 
Reply
sdevost

For both Baker and SECC the work has almost been completely tendered and  work has begun on site.

The time to realize large savings from not requiring those facilities to be net zero has passed; it would require major changes to the building envelope that would likely result in us stopping the work on site and incurring delay claims from the contractors. It introduces risk into the project as the net zero component is integrated as part of nearly all trades so multiple trade packages would need to be reviewed.  There may be some opportunities for some small scale changes but the bulk of the cost is already incorporated into the over project.

In order to determine what the cost savings would be it would require a redesign and then re-costing by most of the trades to compare to what we have now.  That will take months to obtain and again, holds up the work on site incurring delay claims for which the City gets nothing.

Both of these projects are currently on budget, on schedule.  Keep in mind too that SECC is mostly DC funded so any changes to reduce the budget would not impact the tax levy.