Do we have a list of the projects that will be delayed and what might be moving forward? Specifically inquiring about the Hanlon Expressway Underpass Project on the East side of the Hanlon at Kortright.
Reply
Daisy Zhang DaisyZhang
The Hanlon Creek Underpass project was not included in the capital forecast prior to 2024. Over the past two years, due to the unique constraints of the location, staff worked with the Ministry of Transportation and Hydro One to make short term improvements to address hazards. These repairs did not resolve accessibility concerns, but they helped us identify a gap in our Active Transportation Network and we have begun designing a solution. While the design work is nearly complete, no budget has been identified for construction in 2026. The estimated construction costs are expected to be in the range of $160,000 - $200,000. This work is tentatively forecasted for 2028 based on capital budget projections within account PO0033.