If staff could please outline the implications of pausing or cancelling the Emma to Earl bridge, it would be appreciated.
Reply
wmcquade

The strategic plan sets us on a path to make it easier to get around by building a transportation system that works for everyone and offers a variety of travel options for different needs and abilities. A key goal is to increase the non-auto mode share (percent of daily trips made by foot, bike or  bus). A key component is building the Cycling Spine Network recommended in the Transportation Master Plan to deliver a grid network of All Ages and Abilities cycling connections to major destinations.

The Emma-Earl Bridge, identified in both the Guelph Trail Master Plan and Transportation Masterplan and subject to an approved Environmental Assessment, is an essential east-west connection for non-auto trips because the City is unable to provide these facilities over the river on Speedvale. It also provides a key connection to the downtown trail from Riverside park and will be an important crossing for non-auto travel when the Speedvale Bridge is removed for replacement (planned for 2026).

Without the bridge, there will not be a suitable east-west crossing of the river, which will result in impacts to cyclist and pedestrian safety. Further, during reconstruction of the Speedvale bridge, the detour for non-auto users will be significant (roughly a 2 kilometre detour north and nearly a 4 kilometre detour south), which greatly reduces level of service for non-auto travel choices and reduces equity in city service.

Other impacts include lost opportunity to provide infrastructure necessary to meet the City’s council-approved mode share targets (which also is counter to environmental goals for emission reductions), lost opportunity to improvement the environment through removal of historical fill placed in the river valley, and lost place making opportunity.

Other risks associated with removal or deferral of the bridge include increased risk of severe or fatal collisions involving cyclists and pedestrians (counter to the City’s vision zero goals), and financial risk as the bridge will cost more to build in the future should it be deferred. From a financial perspective, although removal/deferral of this project would remove $5.789M from the multi-year budget (with a mix of funding sources impacted), there is also a sunk cost impact of approximately $275,000, not including existing issued contracts valued at an additional $465,000, which carry litigation risks to cancel that has not been evaluated. There is also sunk cost in terms of substantial staff time invested in this project over the past 7 years.

In terms of project status, the bridge has been subject to substantial community engagement, Indigenous engagement, and extensive consultation and negotiations with the Ministry of Indigenous Affairs and Ministry of Environment, Conservation, and Parks, including Ministerial review. This work has been complex, requiring intergovernmental engagement with both ministries to arrive at the current project status. Currently, preliminary design activities are underway, with the detailed design finalizing in 2024 and construction tender to be awarded late 2024 for 2025 construction so that the bridge is in place before the Speedvale bridge comes offline.